Construction work near Expressway (NEXCO CENTRAL area)
Requests for nearby construction work
Construction and work carried out by neighboring municipalities, landowners, etc. within an area that affects Expressway is called adjacent construction. Accidents and incidents caused by adjacent construction not only affect Expressway facilities, but can also lead to irreparable damage to workers and Expressway users. For this reason, if you are planning to carry out adjacent construction work within an area that may affect Expressway managed by our company, we ask that you meet with us in advance and take the necessary steps to ensure safe construction.
Furthermore, in order to prevent accidents due to nearby construction work, we may ask you to hold consultations early and take necessary safety measures, so we ask for your understanding and cooperation.
Please contact the relevant office directly for inquiries regarding occupancy work to be carried out within Expressway area.
Examples of adjacent construction
Please contact us in advance if you are carrying out excavation work, work using heavy machinery, work using scaffolding, or work that will affect Expressway, or work that will result in traffic restrictions on the main Expressway.
- (1) New construction, reconstruction, demolition and repair of buildings
- (2) Felling of standing bamboo and trees
- (3) Inspection, repair, replacement, painting, etc. of roads and bridges
- (4) Embankments and cuts associated with residential land development, etc.
- (5) Installation and replacement of utility poles, installation, removal and replacement of overhead lines, etc.
- (6) Installation and removal of underground pipes
- (7) Work carried out above the tunnel
How to apply
送付アドレス:kanri@c-nexco.co.jp
※お客さまからのメールの確認や返信は、平日の9:00~17:00の間におこなっております。
土・日・祝日および年末年始(12月29日~1月3日)の間は業務をおこなっておりません。
お問い合わせいただいたタイミングや内容によっては、回答までにお時間をいただく場合がございますので、あらかじめご了承をお願いいたします。
(2)近接施工協議が必要と判断された場合には、下記「申請書類(例)」に記載の書類を作成いただき、担当者までご提出をお願いいたします。
※「近接工事問い合わせフォーム」の送付時点で(2)に関する計画図面などのご用意がありましたら、(1)の送付とあわせて所定のアドレスまで参考提出いただいても差し支えありません。
Application documents (example)
| document | Content | Format and example | |
|---|---|---|---|
| Adjacent construction consultation application form | Please fill in the prescribed form with the applicant's name, purpose, location, summary, etc. | Download form Example |
|
| Construction overview | Please use this as a reference for understanding the outline of nearby construction work. | Free style | |
| Location map | Please indicate the areas to be discussed in red on a map that identifies the city, town, village, street, and direction. | Free style | |
| Current situation map Road map |
Plan view | Please indicate the areas to be discussed in red on a map that identifies the city, town, village, street, and direction. | Free style |
| Longitudinal and transverse views | Please clearly indicate the construction location, planned height, distance from Expressway, etc., and prepare a drawing that shows the impact on Expressway | Free style | |
| Provisional design drawing | (When installing temporary structures such as scaffolding) Please clearly indicate the installation location, planned height, distance from Expressway, etc., and prepare a drawing that shows the impact on Expressway (may be combined with the plan drawing and longitudinal and cross-sectional drawings). | Free style | |
| Heavy machinery layout | (When using heavy machinery) Please clearly indicate the location of the heavy machinery, its height, range of movement, range of work, distance from Expressway, etc., and prepare a drawing that shows the impact on Expressway (may be combined with the plan drawing and longitudinal and cross-sectional drawings). | Free style | |
| On-site photos and shooting direction map | Please submit a photograph showing the relative positions of the construction site and Expressway, as well as a drawing showing the direction in which the photograph was taken. | Free style | |
| Process sheet | Please clearly indicate the process of adjacent construction work (if multiple types of work are being carried out, please divide them into categories and clearly indicate the required period). | Free style | |
| Emergency Contact System Chart | Please fill in the designated form with the names and contact information of relevant departments of NEXCO CENTRAL, the owner, the contractor, relevant organizations, etc. | A representative will send you the required form at a later date. | |
| Safety Measures Summary | Please use this as a reference for understanding the outline of safety measures. | Free style | |
| Other required documents | Depending on the characteristics of the construction or work you are discussing, we may ask you to submit documents necessary for discussions regarding nearby construction. | Free style | |
frequently asked Questions
Depending on the work content, such as proximity to cables within an Expressway area, it may take longer, so please contact us well in advance regardless of the above periods.
However, costs of temporary structures, costs related to traffic control, and costs required for protecting Expressway structures will be borne by the parties to the negotiations.
for example
When working on side roads or buildings adjacent to Expressway (including drone operations)
When working on structures that cross Expressway (such as an overpass)
When working under Expressway (bridges, culvert boxes, etc.)
When working above the tunnel